Location: Western Turner Syncline 2 near Tom Price, WA
Client: Rio Tinto
Duration: May 2023 – July 2023
A nice simple project delivering a flood management solution so the S17 Haul Road can remain operational all year round when the creek floods.
- Clearing, grubbing and topsoil stripping, load and haul to stockpile;
- Foundation preparation;
- Remove unsuitable material;
- Construct a culvert mound;
- Excavate a trench;
- Supply and install 2no. barrel 2.4m diameter x 110m long CSP culverts (wrapped and joined);
- Install a concrete tie down block on the inlet/upstream end;
- Cement stabilised fill;
- Embankment construction;
- Stream training;
- Install geotextile and rock protection.