Location: Western Turner Syncline 2 near Tom Price, WA
Client: Rio Tinto
Duration: June 2024 – October 2024
A great project to have been a part of. The team appreciated being part of the discussions to co-design on the scope variations. We received early access to site to suit continuity of works, maintaining our skilled workforce. The works varied with road pavements to suit HME and to suit light vehicles, as well as an electrical equipment pad and extending the tray change out pad for a future office. All whilst maintaining segregation and traffic management with traffic guidance schemes developed to comply with AS1742.3:2019, the MRWA Traffic Management for Works on Roads Code of Practice, and the Austroads Guide to Temporary Traffic Management Part 3 for Static Worksites.
- Demolish existing guardrail and signage;
- Clearing, grubbing and topsoil stripping;
- Establishing a borrow pit;
- Foundation preparation;
- Borrow to fill – select fill and basecourse;
- Excavate drains;
- Cut to fill;
- Place and compact;
- Culvert installation of DN900, DN750, DN600 and DN450;
- Install geotextile and rock protection;
- Trim subgrade and batters;
- Road pavement construction;
- Construct windrows;
- Trim basecourse;
- Rehabilitate the borrow pit;
- Install new guardrail and signage;
- Directional drilling for a new construction water HDPE pipeline.