by Alvin Lai | Dec 1, 2024
Location: Paraburdoo, WA Client: Rio Tinto Duration: November 2024 – December 2024 The team quickly mobilised to site to construct a pad in the pit within 2 weeks, before the tank installation contractor arrived on site. Additional volume of mine waste was...
by Alvin Lai | Oct 1, 2024
Location: Western Turner Syncline 2 near Tom Price, WA Client: Rio Tinto Duration: June 2024 – October 2024 A great project to have been a part of. The team appreciated being part of the discussions to co-design on the scope variations. We received early access...
by Alvin Lai | Apr 1, 2024
Location: Solomon near Tom Price, WA Client: Fortescue Duration: Feb 2024 – April 2024 Our first contribution to Fortescue’s decarbonisation plan. 3no. pads and accesses, working ahead of other contractors installing the power poles and substation kiosks,...
by Alvin Lai | Feb 1, 2022
Location: Greater Rhodes Ridge near Newman, WA Client: Rio Tinto Duration: November 2021 – February 2022 Construction of Baker’s North Laydown Area, including the associated access roads, delineation windrows, drainage and sedimentation pond. Clearing,...
by Alvin Lai | Feb 1, 2022
Location: Paraburdoo, WA Client: Rio Tinto Duration: January 2021 – February 2022 As the Northern Cell’s eastern tailings deposition pipeline feeds the Southern Cell, it had to be relocated outside of the raise’s embankment footprint for the Southern...