Solomon Civil Works – Liebherr R9400E Electrical Infrastructure

Solomon Civil Works – Liebherr R9400E Electrical Infrastructure

Embankment construction of 3no. pads to facilitate the installation of electrical infrastructure by others, as part of the decarbonisation plan.
Detailed earthworks, constructing an access to a pad in the Pilbara

Location: Solomon near Tom Price, WA

Client: Fortescue

Duration: Feb 2024 – April 2024

Our first contribution to Fortescue’s decarbonisation plan. 3no. pads and accesses, working ahead of other contractors installing the power poles and substation kiosks, which will power the new Liebherr R9400E electric excavators.

  • Clearing, grubbing and topsoil stripping, load and haul to stockpile;
  • Foundation preparation;
  • Cut to Fill;
  • Borrow to Fill – Select fill and Basecourse materials;
  • Road pavement construction;
  • Supply and install 4no. pre-cast concrete strip footings for substation kiosk foundations;
  • Supply and install 1no. barrel 600mm diameter x 33m long CSP culverts (wrapped and joined);
  • Cement stabilised fill;
  • Install geotextile and rock protection;
  • Excavate V-drains (including rock breaking);
  • Supply and install blue metal;
  • Supply and install electrical conduit;
  • Construct windrows.

cubic metres moved

metres of culverts installed

metres of conduit installed