Paraburdoo Tailings Storage Facility TSF1 Northern Cell

Paraburdoo Tailings Storage Facility TSF1 Northern Cell

Upstream embankment raise of TSF1 Northern Cell, 2m high, including the decommissioning of existing and commissioning of new pipework.
Bulk earthworks, constructing a tailings dam in the Pilbara

Location: Paraburdoo, WA

Client: Rio Tinto

Duration: January 2021 – February 2022

As the Northern Cell’s eastern tailings deposition pipeline feeds the Southern Cell, it had to be relocated outside of the raise’s embankment footprint for the Southern Cell to remain operational during construction of the Northern Cell. Whereas the remaining existing pipework could be decommissioned, to facilitate the raise using Zone 1B material from the borrow area for containment embankments and General Fill material from Pit 18E Waste Dump everywhere else – perimeter roads along natural ridges, some of which involved excavating hard rock, and the decant causeway.

  • Clearing, grubbing and topsoil stripping;
  • Establishing a borrow pit;
  • Excavate key in tailings;
  • Foundation preparation;
  • Strip existing wearing course and stockpile for re-use;
  • Condition, load and haul;
  • Place and compact;
  • Excavate drains;
  • Trim subgrade and batters;
  • Road pavement construction;
  • Construct windrows;
  • Trim wearing course;
  • Rehabilitate the borrow pit;
  • Construct an emergency spillway;
  • Construct low level crossings with overflow drains;
  • Source rock via screening and rock breaking;
  • Install geotextile and rock protection;
  • Install pre-cast concrete box culverts for pipe crossings;
Bulk earthworks, constructing a tailings dam in the Pilbara
  • Install guideposts and delineators;
  • Install signage;
  • Extend existing VWP cables to new data loggers;
  • Install concrete survey monitoring points;
  • Install flood level indicators;
  • Procure hydraulic-actuated and manual handwheel knifegate, butterfly, non-return, ball, pressure sustaining, flow control valves, OD400 (DN400) SDR9 PN20 PE100 HDPE pipe, OD355 (DN350) SDR17 PN10 PE100 HDPE pipe, OD315 (DN300) SDR11 PN16 PE100 HDPE pipe, OD180 (DN150) SDR17 PN10 PE100 HDPE pipe, Table F and Table E backing rings, reducers, tees, sweep bends and elbows, gaskets, stud bolt sets, mining hose, pre-cast concrete pipe supports and pipe anchors with HDPE liners, HDPE-lined steel pipe and Victaulic couplers, electric pump, Variable Speed Drive (VSD), diesel fuel tank, TruFlo pumps, suction turrets, solar-powered telemetry skids, pressure transmitter, flow transmitter, level transmitter and burst discs.
Polywelding and pipeworks installation, constructing a tailings dam in the Pilbara
Polywelding and pipeworks installation, constructing a tailings dam in the Pilbara
  • Polyweld and install kilometres of tailings pipeline – HDPE-lined steel, HDPE, and slotted spigots.
  • Polyweld and install kilometres of decant water pipeline and additional emergency decant line;
  • Polyweld and install kilometres of return water pipeline;
  • Hydrostatic pressure test;
  • Install 140no. valves;
  • Modify existing steel and HDPE pipework, cut and weld on site;
  • Install 1no. electric pump;
  • Install 1no. VSD;
  • Install 1no. diesel fuel tank;
  • Install 2no. TruFlo pumps;
  • Install 15no. pieces of instrumentation – pressure, flow, level, burst;
  • Install 3no. solar-powered telemetry skids;
  • Modify the Motor Control Centre (MCC) and tie-in;
  • Electrical installation and testing;
  • Energise and commission;
  • Decommission temporary tailings deposition pipeline;
  • Plug existing culverts.
Polywelding and pipeworks installation, constructing a tailings dam in the Pilbara

cubic metres moved

kilometres of access roads

kilometres of pipeworks installed

valves installed

concrete items installed

VSD installed

pumps installed

diesel tank installed

instrumentation installed

solar-powered telemetry systems

hectares of rehabilitation