Location: Tom Price Mainline (29KP) near Karratha, WA
Client: Rio Tinto, Calibre
Duration: July 2018 – July 2018
Works included the removal and replacement of the existing rail formation during a Mine Shut under 50 hours. Works passed through a Super Site consisting of numerous various instrumentation.
- Removed 850 m of rail formation;
- Constructed 1.35 km of rail formation to strict levels;
- Placed geotextile and geogrid prior to sub-ballast capping and ballast;
- Remediate set of existing culverts with cement stabilised fill;
- Nil incidents.
metres of rail embankment renewed
square metres of geotextile/geogrid