Location: Paraburdoo, WA
Client: Rio Tinto
Duration: August 2019 – February 2020
Screened bulked-out iron ore stockpiled on Stockpile 5 in the Paraburdoo Stockyards. Screened iron ore spillage stockpiled near the “S-bend”. Screened iron ore spillage stockpiled at the Train Load Out (TLO). Screened iron ore spillage stockpiled at Eastern Range. All screened iron ore was reintroduced to the plant conveyor system instead of stockpiling for the mine to rehandle. Ran day shift and night shift to achieve the mine’s SOP targets during a time when the stockyard was undergoing an upgrade with new reclaimers and stackers. And worked around shuts and conveyor stoppages.
- Set-up mobile screen with self-cleaning overband magnet and ROM wall and ramp;
- Load and haul with moxies when segregated from LV traffic;
- Load and haul with side tippers whilst using LV access roads;
- Dust suppression and access road maintenance for the stockyard.